Free snagging list template
A snagging list records the small defects left at the end of a building, fit out or repair job, and who will put each one right. Site managers, contractors and clients use one at handover so nothing is argued about later. This template has one row for each snag, with its location, a description, the trade responsible, a priority, a due date and the date it was closed.
Free to use and change. No sign up and no email address needed.
The snagging list template
| No. | Location | Snag | Photo ref | Trade or contractor | Priority | Raised on | Due by | Status | Closed on |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Ground floor, reception | Paint run on wall to left of main door | IMG 0141 | Decorator | Low | 09/11/2026 | 20/11/2026 | Closed | 18/11/2026 PS |
| 2 | Ground floor, reception | Floor box lid does not sit flush | IMG 0142 | Example Electrical | Medium | 09/11/2026 | 16/11/2026 | Closed | 16/11/2026 PS |
| 3 | Ground floor, WC 1 | Silicone missing behind basin | IMG 0147 | Plumber | Medium | 09/11/2026 | 16/11/2026 | Fixed | |
| 4 | First floor, kitchen | Wall unit door out of line, far right | IMG 0150 | Joiner | Low | 09/11/2026 | 20/11/2026 | Open | |
| 5 | First floor, open plan | Ceiling tile stained by column C4 | IMG 0153 | Ceiling fixer | Medium | 09/11/2026 | 16/11/2026 | Open | |
| 6 | First floor, meeting room 2 | Door closer slams, needs adjusting | IMG 0155 | Joiner | High | 09/11/2026 | 12/11/2026 | Closed | 12/11/2026 PS |
| 7 | Stair A, half landing | Emergency light fitting has no test label | IMG 0158 | Example Electrical | High | 09/11/2026 | 12/11/2026 | Fixed | |
| 8 | Roof | Loose cable tray cover near AHU1 | IMG 0161 | Example Electrical | Medium | 09/11/2026 | 16/11/2026 | Open |
What each column is for
- No.
- A running number, so everyone can refer to the same snag.
- Location
- The floor and room, and where in the room.
- Snag
- What is wrong, clearly enough that someone else can find it and fix it.
- Photo ref
- The file name or number of the photo you took of it.
- Trade or contractor
- Who is responsible for fixing it.
- Priority
- High, Medium or Low, under meanings you have agreed.
- Raised on
- The date the snag was recorded.
- Due by
- The date it should be fixed by.
- Status
- Open, Fixed or Closed. Closed means it was checked after the fix.
- Closed on
- The date it was checked and accepted, with initials.
How to use it
- Walk the job in order. Go floor by floor and room by room in the same direction each time, so nothing is missed.
- Write each snag on its own row. Say exactly where it is and what is wrong. Take a photo and note its number.
- Name who fixes it and by when. Agree the trade, the priority and a due date for each snag before you leave site.
- Send the list out. Give every contractor the same list, so they can see their own snags and everyone else's.
- Check and close. Walk round again after the due date. Mark a snag Closed only when you have seen the fix.
Use the live version
A snagging list goes out of date the moment someone fixes something. In OmniSchema Operations each snag can be a job with an owner.
- Anyone can report a fault on a simple page: a title, the site and what is wrong.
- Your team sets the priority and gives the job to an engineer, who starts and closes it on their phone.
- The history records who started and closed each job and when.
- On the paid plans your clients can report faults and follow their own jobs in a customer portal.
OmniSchema Operations has a free plan with no card needed. See pricing.
Questions people ask
What is a snagging list?
It is a list of the small defects and unfinished items found when a job is inspected near the end. Each one is recorded so the contractor can put it right before final handover.
What should a snagging list include?
A number, the location, a clear description, a photo reference, who is fixing it, a priority, a due date and a status.
When should snagging be done?
Usually when the contractor says the work is complete and before you accept it. A second walk round checks that the fixes were done.
Should I take photos of snags?
Yes. A photo with a reference on the list saves arguments about where a snag is and what it looked like.
Who closes a snag?
Whoever raised it, or the client's representative, after seeing the fix. The trade marks it Fixed, and the checker marks it Closed.