Free template

Free RAMS register template

A RAMS register is a list of the risk assessments and method statements you have received or written, and whether each has been reviewed and accepted. Site managers, facilities managers and contractors use one to make sure no job starts on an unchecked or out of date document. This template has one row for each document, with the job, the contractor, the version, who reviewed it, the outcome, and when it was briefed to the people doing the work.

Download Excel (.xlsx)Download PDF

Free to use and change. No sign up and no email address needed.

What this template is not. This register tracks documents. It does not replace the risk assessments themselves, or the judgement of a competent person reviewing them.

The RAMS register template

Example rows. The sites, firms and names are made up.
RAMS refSite and jobActivityContractorVersionReceivedReviewed byOutcomeAccepted onBriefed onReview byNotes
RAMS-0228Ashby House, J-20925Emergency lighting repairs at heightExample Electrical110/11/2026Priya S.Accepted11/11/202619/11/202611/11/2027
RAMS-0229Ashby House, J-20941Lift motor room maintenanceExample Lifts312/11/2026Priya S.Accepted13/11/202617/11/202613/11/2027
RAMS-0230Example Court, J-20940Replace section of cold water mainExample Mechanical116/11/2026Priya S.ReturnedNo isolation plan. Asked for version 2
RAMS-0231Example Court, J-20947Hot work on chilled water pipework, roofExample Mechanical219/11/2026Priya S.Accepted20/11/202624/11/202620/11/2027Permit PTW-0087
RAMS-0232Example Court, J-20948Roof gutter clearanceOwn team420/11/2026Dana W.Accepted20/11/202623/11/202620/05/2027Reviewed after edge protection changed
RAMS-0233Unit 4, Mill Lane, J-20911Roller shutter spring replacementPennywick Doors113/11/2026Dana W.Accepted16/11/202617/11/202616/11/2027
RAMS-0234Unit 4, Mill Lane, J-20955Racking inspection and repairsDunmarrow Storage120/11/2026Dana W.ReturnedCovers a different site. Asked for a site specific version

What each column is for

RAMS ref
Your own running reference for the document.
Site and job
Where the work is and the job it belongs to.
Activity
The work the document covers.
Contractor
Who wrote it and will do the work.
Version
The version or revision on the document, so an old copy is not used by mistake.
Received
The date you received this version.
Reviewed by
Who checked it for your organisation.
Outcome
Accepted, or Returned with the reason in Notes.
Accepted on
The date this version was accepted.
Briefed on
The date the people doing the work were briefed and signed it.
Review by
The date it should be looked at again if the work is still going on.
Notes
Why it was returned, linked permits, or changes on site.

How to use it

  1. Give every document a reference. Number each risk assessment and method statement as it arrives, and save the file under that number.
  2. Record the version. Write the version from the document. When a new version arrives, update the row and keep the old file.
  3. Review before the work is booked. A competent reviewer checks it is specific to the site and the job, then marks it Accepted or Returned.
  4. Record the briefing. Note the date the people doing the work were taken through it and signed it.
  5. Check the register before work starts. No Accepted outcome and briefing date, no start. Set a review date for work that carries on.

Use the live version

The register is most use when it sits beside the jobs. With the Field Job Tracker kit in OmniSchema Operations, engineers log a job, start RAMS and close it out on their phone.

  • Engineers see their own jobs for the day on their phone and close them without ringing the office.
  • A safety check before the job starts, and your own close out questions, photos and notes before it ends.
  • It keeps working with no signal and sends everything when the phone is back online.
  • On the paid plans each closed job has a job sheet PDF, with the customer's signature if you ask for one.
Start free and install itPreview the Field Job Tracker kit

OmniSchema Operations has a free plan with no card needed. See pricing.

Questions people ask

What does RAMS stand for?

Risk assessment and method statement. The risk assessment sets out the hazards and controls, and the method statement describes how the job will be done safely, step by step.

What is a RAMS register for?

It shows at a glance which documents you hold, which version is current, whether each has been reviewed and accepted, and whether the workers have been briefed.

Who should review RAMS?

Someone competent who knows the site and the kind of work. Their task is to check the document fits this job in this place, not to rewrite it.

How often should RAMS be reviewed?

Whenever the job, the site or the method changes, and at an interval you set for work that carries on. Record the date in the Review by column.

What should I do with generic RAMS?

Return them. A document that does not mention your site, its hazards or the actual job has not assessed the risk of the work you are about to allow.